Free calculator · Workshops & manufacturing
How much of the shift turns into good parts?
OEE combines three losses: machines standing still, running below the ideal pace, and scrap. Enter the figures of one shift and see where the time goes.
OEE of the shift
69.3%
312 min of good parts out of 450 min planned
- Good parts 312 min
- Stops 45 min
- Slow running 85 min
- Scrap 8 min
- Availability405 min running out of 450 min planned
- 90.0%
- Performance320 min of work at the ideal pace in 405 min
- 79.0%
- Quality312 good out of 320
- 97.5%
- Time lost in the shiftstops 45 min · slow running 85 min · scrap 8 min
- 138 min
The example is already filled in: change the figures and the result updates. The sum runs in your browser: nothing is sent or saved.
How it is worked out
Three steps, with the example’s figures.
Availability
The time the machine ran over the planned time: (480 − 30 − 45) ÷ (480 − 30) = 405 ÷ 450 = 90%.
Performance
The time the work would have taken at the ideal pace over the running time: 320 pieces × 60 seconds = 320 minutes, out of 405 = 79%.
Quality and OEE
Good parts over the total: 312 ÷ 320 = 97.5%. OEE is the product of the three: 90% × 79% × 97.5% = 69.3%, that is 312 minutes of good parts out of 450 planned.
With Taktra
In Taktra availability comes from the stoppages you already record.
The Efficiency page works out availability, hours lost, breakdowns, time between breakdowns and time to restart, machine by machine, over the last 7, 30 or 90 days, with stop causes ranked by weight. Nothing new to fill in.
- Stoppages with cause and duration, recorded on the floor
- Stop causes ranked by weight, with the running share
- Hours lost also estimated in euros
Questions
Before you trust a number.
What is a good OEE?
85% is the benchmark used for the best lines. Many manufacturers sit around 60%, and below 40% more time is lost than used. More than the absolute value, what matters is how it moves, month after month, on the same machine.
What should I enter as the ideal cycle time?
The fastest pace the machine can sustain on that part: from the spec sheet, the program or your best shift. If you set it too slow, performance looks better than it is.
Do set-ups count as planned stops?
Usually not: in OEE set-ups reduce availability, and they should show, because cutting them is one of the quickest ways to gain hours. Breaks and meetings, on the other hand, are planned stops.
Other free calculators
Production capacity
The hours you really have this week, and whether they cover the work to do.
OpenRealistic delivery date
The day the work is ready, with Saturdays, public holidays and closures.
OpenFood cost of a dish
Cost per portion, food cost before VAT and the lowest price for your target.
OpenShift cost
Staff cost per week, per month and per opening hour.
OpenGive your work
its shape.
Thirty days to see whether your team really uses it. Open Taktra in your browser, create your company and describe how you work.
No card needed to start: 30 days free, then you decide whether to subscribe.