Free calculator · Workshops & manufacturing
What date can you promise without gambling?
Working hours, hours per day, Saturdays, public holidays and closures: the day the work is really ready, and whether you make the date the customer asks for.
Ready for delivery
Wednesday, 2 December 2026
after 6 working days
- Work
- Closed
- Ready
- Date asked
- Working hours20 pcs × 90 min + 4 h set-up
- 34 h
- With contingency+10%
- 37.4 h
- Working daysat 7 h a day
- 6
- Calendar days2 skipped for weekends, holidays and closures
- 8
The example is already filled in: change the figures and the result updates. The sum runs in your browser: nothing is sent or saved.
How it is worked out
Three steps, with the example’s figures.
Working hours
Pieces × time per piece, plus set-up: 20 × 90 minutes = 30 hours, plus 4 = 34 hours.
Contingency
10% more covers stoppages, absences and rework: 34 hours + 10% = 37.4 hours.
Days on the calendar
Hours divided by hours per day, rounded up: 37.4 ÷ 7 = 5.3, so 6 working days. The calendar skips Sundays, Saturdays if you do not work them, public holidays and closures.
With Taktra
In Taktra the date moves by itself when something changes.
Every job has its expected date, calculated from today’s real capacity: machines, people present, public holidays, closures, stoppages, maintenance and incoming materials. If the date passes the promise to the customer, you see it at once.
- Expected date of every job, recalculated at every change
- Filters for late, at-risk and on-track jobs
- The customer’s order, by email or PDF, read by AI and set up as a job
Questions
Before you trust a number.
Why add a contingency?
Because estimated hours are nearly always optimistic: a stoppage, an absence or a part to remake use up time nobody allowed for. 10–20% saves you calling the customer to move the date.
Which public holidays does it count?
Italian national public holidays: New Year’s Day, Epiphany, Easter Monday, 25 April, 1 May, 2 June, 15 August, All Saints, 8 December, Christmas and St Stephen’s Day. The local patron saint’s day changes from town to town: enter it as a company closure.
What if the work goes through several machines or departments?
The calculator assumes a single resource, with the hours per day you give it. If the work goes through several stages, do the sum stage by stage and start from the slowest. In Taktra the calculation runs by itself, stage by stage, on each station’s capacity.
Other free calculators
Production capacity
The hours you really have this week, and whether they cover the work to do.
OpenOEE of a shift
Availability, performance and quality: where machine time goes.
OpenFood cost of a dish
Cost per portion, food cost before VAT and the lowest price for your target.
OpenShift cost
Staff cost per week, per month and per opening hour.
OpenGive your work
its shape.
Thirty days to see whether your team really uses it. Open Taktra in your browser, create your company and describe how you work.
No card needed to start: 30 days free, then you decide whether to subscribe.